Rocklin pipeline replacement project along Midas Avenue getting underway

SourcePCWA

PCWA Begins Phase 1: Providing Long-Term Water Reliability

Rocklin, Calif. – Placer County Water Agency (PCWA) is set to begin Phase 1 of the Rocklin Pipeline Replacement Project, an important infrastructure upgrade that will enhance long-term water reliability for residents in the City of Rocklin. This phase will focus on replacing an aging water main along Midas Avenue, between 2nd Street and Argonaut Road.

The existing steel pipes, installed in 1963 and coated with cement mortar, have approached the end of their operational lifespan. A series of leaks and failures on the mainline pipes in recent years underscores the importance of this project.

"Replacing these aging pipelines is essential to preventing future disruptions and safeguarding the delivery of drinking water to Rocklin residents," said Associate Engineer Steve Bowman, the Project Manager. "This investment in infrastructure will help reduce costly repairs and improve overall water reliability into the future."

Project Scope and Timeline

Phase 1, scheduled to begin on October 21, focuses on replacing a significant portion of the mainline pipes along Midas Avenue, between 2nd Street and Argonaut Road. The project includes trenching to install a new 12" mainline pipe, service laterals, and meter boxes. After pressurizing the mainline and connecting individual residences, crews will backfill the trench and apply temporary pavement. Final paving and striping will be completed once the entire road section is ready. The work will progress in sections along the route to minimize disruption. Construction is expected to conclude by Summer 2025.

Traffic and Service Impacts

Motorists traveling through the construction zone should expect delays during construction hours. Two-way, controlled traffic will be maintained, Monday through Friday, 8 a.m. to 3 p.m., but construction activities on-site may last from 7 a.m. to 4 p.m. Traffic flow is expected to be slower than usual, so please plan accordingly. Flaggers will be on-site to assist with pedestrian access. Temporary no-parking signs will be placed ahead of each construction section, as the work zone will shift along the route. Water service will remain largely unaffected, with only brief interruptions anticipated as crews tie in the new pipes. Residents will receive 72-hour notice of any planned shutoffs.

"We understand that construction can be an inconvenience, and we truly appreciate the community's patience as we work to improve Rocklin's water infrastructure," said Bowman. "These temporary delays will result in long-term benefits, ensuring reliable water service for years to come."

Background

Originally scheduled to start in August 2023, Phase 1 was delayed due to supply chain issues involving critical components, such as brass fittings and valves. In light of significant disruptions caused by the severe storms of 2023, PCWA reconfigured the project timeline to lessen inconveniences for residents. As a result, Phase 2, which focused on the pipeline section between Clover Valley and Argonaut Road, was initiated first and successfully completed in July 2024.

With an estimated cost of $3.1 million for Phase 1, the overall multi-phase project is expected to total $24 million when finished. This investment, funded by PCWA ratepayers, will provide the Rocklin community with a renewed, reliable water infrastructure system that will last for decades.

More Information:
For more details and updates, visit pcwa.net/RocklinMain or contact Project Manager Steve Bowman at (530) 823-4881 or [email protected].


Become a Sustaining Patron

100% voluntary • Cancel anytime • No paywall

Roseville Today remains free for everyone.
Your voluntary monthly support helps us continue serving the community.

Pumpkin Patches

Local Insights

Trending

Roseville Police Warn Residents: How to Stay One Step Ahead of Scammers

Roseville Police Department shares important scam prevention tips to help Roseville residents recognize imposter scams, investment fraud, suspicious messages and other common scams.

New Rapid Link Bus Service Connects Lincoln, Roseville and Sacramento Light Rail Starting October 1

Roseville, Calif. - Rapid Link, an express transit service operated by Roseville Transit, is scheduled to begin service Thursday, October 1, 2026, connecting Lincoln, Roseville and the Watt/I-80 Light Rail Station in Sacramento.

New Alchemy Surf Resort Coming to Edge of Roseville, Rocklin, & Lincoln

Roseville, Calif.- The Placer County Planning Commission has approved plans for the Alchemy Surf Resort, a new recreational surf and hospitality destination planned within the Placer One development.

Volunteers in Rocklin Pack 426,168 Meals for Malnourished Children

Rocklin, Calif. - Nearly 2,000 volunteers packed 426,168 meals for malnourished children at the 16th annual Placer Feed My Starving Children MobilePack, held Sept. 17-19 in Rocklin.

Pumpkin Patches in the Roseville area and beyond

"There are three things that I've learned never discuss with people: religion, politics, and the Great Pumpkin." says Linus from Charlie Brown

Updated: Spirit Halloween locations in Roseville for 2026

Roseville, Calif. - This week is the arrival of Autumn and that means Halloween isn't far behind. Spirit Halloween superstores are open in Roseville with a total a 3 locations. This year, Rocklin does not currently have a location listed.

Hope Valley: California's Autumn Wonderland

Alpine County, Calif. - Draped in hues of golden yellow and pumpkin orange, groves of aspen trees shimmer with the arrival of fall. This is Hope Valley, California — a fall foliage wonderland where October

Woodcreek High School in Roseville Seeks Dress Donations for Formal Wear Event

Woodcreek High School's Wellness Center is seeking formal dress donations for its second annual Formal Wear Event, helping students find outfits for Homecoming regardless of income.

Ain't Necessarily Dead Fest in Auburn: Placer County's Most Colorful & FREE Event this Saturday

Ain't Necessarily Dead Festival returns to Auburn at Regional Park on September 12, 2026 for another legendary day of music, dancing and a cosmically good time in the time-honored tradition of any Deadhead gathering.

Roseville Polish Festival: Annual Celebration Returns September 12, 2026

Roseville, Calif.- The public is invited to attend the Annual Polish Festival in Roseville, California on Saturday, September 12, 2026.

Related Articles

Sponsored Local Spotlight

Roseville Sheet Metal serving community's heating and air needs for over 70 years

Roseville, Calif. - At Roseville Sheet Metal, we’re proud of our years of service to the Roseville area and look forward to helping you with your air conditioning and heating needs.

Sacramento Naturopathic Medical Center emphasizes the use of prevention and natural therapeutics

Sacramento Naturopathic Medical Center is a professional primary care natural medicine committed to helping all people reach their full potential – mind, body and spirit.

Mobley Pest Services in Roseville serving the community and region for over 20 years

Roseville, Calif.- Fully licensed and bonded, Mobley Pest Services in Roseville has been providing reliable pest control services for well over 20 years. Serving residents and businesses in the greater Placer and Sacramento region, Mobley Pest Services is locally owned and operated in Roseville.